Florida Lien Waivers Questions

All Status
Lien Waivers
Florida
Our customer is asking for releases of lien on invoices that we did not send a NTO I told them we are not obligated he keeps coming back. so are we obligated to do it ?...Read More
Anonymous Material Supplier
Waiting for answerAdd commentJan 28, 2022
FloridaLien Waivers
I filed a lien on a job. Now all of the sudden my contractor wants me to sign a lien waiver because the bonding agency, owner, general contractor, and material provider all are trying to get paid. My contractor sent over a lien release form. Do I legally have to sign and return this form without being paid first? My concern is that if I sign this the contractor will not provide the check owed. As he is delinquent on another invoice for another job. I am in another state working right now, so doing a person to person exchange is not possible. What are my options. Thank you, Daniel Krek...Read More
Daniel Krek
1 answerAdd commentJan 25, 2022
FloridaLien ReleasesLien WaiversMechanics Lien
To whom it may concern, I filed a lien against a contractor for the non payment of one weeks worth of work. I received a call from the material provider last week. They are who hired the installer who contracted me for part of the install. Then later that day the contractor who hired me was emailing me asking for COI’s stating that is the reason why I had not been paid. So within 24hrs I sent over my COI’s. Now he has sent me a lien release form. It states that if I sign the waiver I will be paid. I have already file the lien, will signing this release negate my lien? Or do I not sign until the payment is made. Thank you, Daniel Krek...Read More
Daniel Krek
3 answersAdd commentJan 19, 2022
FloridaLien ReleasesLien WaiversMechanics Lien
We are a small retail/ecommerce business located in NJ and our customer is as property management in florida. My question is: What amount and date should I state for the 50% down payment upon placing his order. They send us a lien with a format below: WAIVER AND RELEASE OF LIEN UPON PROGRESS PAYMENT (Florida) The undersigned lienor, in consideration of the sum of $_______________, hereby waives and releases its lien and right to claim a lien for labor, services, or materials furnished through ____________ to __________________ on the job of ______________________to the following property: This waiver and release does not cover any retention or labor, services, or materials furnished after the date specified....Read More
Anonymous Contractor
Waiting for answerAdd commentJan 13, 2022
FloridaLien ReleasesLien Waivers
Driveway contracted with mistakes poor workmanship how to address warranty owner will not fix ...Read More
Anonymous Contractor
Waiting for answerAdd commentDec 24, 2021
FloridaLien Waivers
Hello Support, I hope this message finds you well. I had contracted a Painting(Garage & Laundry room and Garage Epoxy Flooring) to a local contractor in Florida (Brevard County). The total cost of the project was about $1850 dollars. The scope of the project outlined in the initial estimate was not followed precisely, but I choose to follow the contractor's professional advice. The issues that arise stem mainly from the epoxy part of the job, having several air pockets on the floor resulting from epoxy not adhering properly. After having a call with Sherwin Williams(Brand of Expoy used) agent, she advised that epoxy should not be poured onto fresh concrete or should be given weeks of drying time before doing so. The pouring of fresh concrete was not part of the scope of the project and it replaced 'repairing of cracks' and acid washing and scoffing the concrete. Anyway, the contractor dealt with all of my objects and the job became almost salvageable. The final aspect of adding the prescribed amount of clear coat (3) was not done in a timely fashion or as per the product specification required. Sherwin William's brand of epoxy clear coat requires additional coats to be added before 72 hours window. Here is the contractor took weeks to respond back to my message after I advised him that I'll get someone else to do finish or redo the job. He finally replied and hurried someone to come finish the job. I told him no one is touching the job unless the specification of Sherwin William is followed;re-scoff before adding clear coat since it was way beyond the application window. He then threatened a Lien on the property via Text. However, we came to an agreement that if he would take the risk of adding the clearcoat and everything turn out favorable after 72 hours he will be paid and so far the finish looks fine. Now before paying him, I need a legal instrument that would protect me from any future threats, and so i was looking at your conditional waiver. Is this the right legal instrument to use? Be advised I've already given him a 50% advance payment as well. Thanks Regards ...Read More
Anonymous Contractor
Waiting for answerAdd commentDec 8, 2021
FloridaLien ReleasesLien Waivers
Here is the situation We are fully installed and currently in the PTO stage. The PTO application was submitted to the utility on 11/02 and is currently awaiting their approval. This does leave us with the chance that the utility could ask for a change to be made on site. We have not been fully paid yet. If the notes on the processing page are correct, we have only received $36.232 and are awaiting further payment of $53.098. The lien release affidavit does give the option to provide a bank account number for the final payment to be transferred to, if we are comfortable providing one....Read More
Anonymous General Contractor
1 answerAdd commentNov 18, 2021
FloridaLien Waivers
my decorator(contractor) hired a tile person (subcontractor) to work in my house. They both had an argument and the contractor fired the subcontractor. I (homeowner) just received a "Claim of Lien" from the subcontractor. I live in Florida. I understand that I should get a waiver of lien but don't know if i get it from contractor or sub contractor. I contracted and paid the contractor ...Read More
Anonymous Contractor
1 answerAdd commentNov 10, 2021
FloridaLien Waivers
We supply materials to customers and jobsites. My customer has paid us $122,500 but didn't pay a couple of small invoices totaling $5,909.99. We want to give them a conditional progress payment release with the outstanding amount of $5,909.99 due. The form I populated shows Maker of check xxxxxxx Amount of check $5,909.99 Check Payable to xxxxxxxxx We are not swapping this release for the check at this time but want to give them the release so they can get their money, we are waiting their payment to be processed and mailed. Are we covered if we do not require this check as a swap for this document?...Read More
Anonymous Material Supplier
2 answersAdd commentOct 18, 2021
FloridaLien Waivers
A roofing contractor just completed reroofing my home. Do I need a release of lean from the roofer and supplier?...Read More
Anonymous Contractor
1 answerAdd commentSep 9, 2021
FloridaLien Waivers
Stupid question from a new Florida homeowner... Putting a new roof on my home, the job is tile so expensive. The NOC is mandatory? And how soon is the lien released once job is complete and paid in full? Also how do you protect yourself as a homeowner from the Florida Contractors Lien? I know crazy questions. Thank you...Read More
Anonymous Contractor
1 answerAdd commentSep 14, 2021
FloridaLien WaiversNotice of Commencement
Hello Good afternoon, Small business here. Payment finally came through after 95 days after work completion. Due to contract finishing touches are to be made and they are withholding $7,000 but want the lien waiver signed yesterday...Read More
Anonymous Contractor
3 answersAdd commentSep 9, 2021
FloridaLien Waivers
What can be done if a preliminary lien notice has been filed to the incorrect name, parcel number and address? ...Read More
Anonymous Contractor
1 answerAdd commentSep 4, 2021
FloridaConstruction ContractLien Waivers