I'm an electrical contractor. We design and build energy projects for home owners like pv, storage, generators. Also do service and other elec work. Supply chain struggles dictate that we have to purchase from many vendors now. New ones demand payment in full to ship. Huge strain on our cash. Have considered the usual deposit at signing of lesser of 10% or 1 k and then billing for the equipment we have to special order, minimally 4 business days after contract signing. ...Read More
Anonymous Contractor
1 answerAdd commentApr 25, 2022
CaliforniaConstruction Accounting
Hello, I'm GC and sub at this project and regardless of the other notices I sent for GC/sub related to my scope of work, the property owner received a $632K loan from us. How can i protect this amount? please advise. ...Read More
Anonymous Subcontractor
1 answerAdd commentApr 18, 2022
California
Just found out about auction,due to late taxs/property tax owed,been on site for over 2yrs. Auction is on line,being held May 10 2022...Read More
Alan Vance
1 answerAdd commentApr 19, 2022
California
Our Mechanics Lien expired on 4/6/2022 when we were in negotiations with the Escrow company to pay. Now they will not pay us due to the expiration of Mechanics Lien. ...Read More
Anonymous Subcontractor
1 answerAdd commentApr 21, 2022
CaliforniaForeclosure
I have a client that are not willing to pay us unless we reciprocally exchange check for unconditional release on final payment. We are located in California and I know that a Unconditional release will leave us without any rights if the check doesn't clear the bank. Are we allowed to add under Exceptions a note that states that this release is only valid upon funds positive deposit or something along these lines? thank you. Monica msafarik@icsinc.tv...Read More
Monica Safarik
2 answersAdd commentApr 18, 2022
CaliforniaCollections
The amount of the lien is limited to the reasonable value of the labor, services, equipment, or materials furnished or for the price agreed upon by the claimant and the person with whom he or she contracted, whichever is less. My question is: who does this refer to, the claimant and the general contractor or the claimant and the owner of the project?...Read More
Anonymous Contractor
1 answerAdd commentApr 20, 2022
California
We filed a preliminary notice in May of 2021, and then filed our lien in April of 2022. We were notified by the property owner that the NOC was filed in July of 2021 so we no longer had lien rights. We were never sent a copy of the NOC , or notified that one was filed. Do we still have lien rights since we weren't notified? ...Read More
Anonymous Laborer
1 answerAdd commentApr 20, 2022
CaliforniaLien Deadlines
I have a client that are not willing to pay us unless we reciprocally exchange check for unconditional release on final payment. We are located in California and I know that a Unconditional release will leave us without any rights if the check doesn't clear the bank. Are we allowed to add under Exceptions a note that states that this release is only valid upon funds positive deposit or something along these lines? thank you. Monica msafarik@icsinc.tv...Read More
Monica Safarik
3 answersAdd commentApr 19, 2022
CaliforniaConstruction Accounting
Hello, Is it possible to file a mechanics lien for unbilled change orders and retention? We have outstanding changes that haven't been approved yet so we are unable to bill for them. And typically we're not able to bill retention until the project has been completed. According to our project manager, all the changes are legitimate, the work has been completed. Our lien rights are going to expire soon so what would we need to do in this situation? Can we still file a lien for everything outstanding?...Read More
Stephanie Soto
1 answerAdd commentApr 19, 2022
California
Private funded project involving roadway improvements for a lot split. The city comes in and request additional work to the city water supply system. The additional work is under a separate contract with the city and is almost $50,000 . Additional work does not improve the property involved. It is performed by the same subcontractor but without any knowledge to the owner of the property in question. Can the Sub file a mechanics lien for the city requested extras without any preliminary notice being sent regarding the extra / separate contract work?...Read More
Anonymous Contractor
1 answerAdd commentApr 18, 2022
CaliforniaMechanics LienPreliminary Notice
Are back charges credited to the customer as well or are the terms only between the GC and Sub? ...Read More
Anonymous General Contractor
Waiting for answerAdd commentApr 18, 2022
CaliforniaBack Charges
Im a subcontractor I gave a proposal to a general contractor, they liked our proposal, signed a contract and I sent out a preliminary notice. I've invested time and money into the project, we started working on the project in November 2021(shoring and bracing), the owners made major changes after they had already signed the contract and now they didn't accept the change order price and they decided to give the job to someone else. What happens when they have canceled the signed contract, are we to be compensated, we have not had a contract canceled before, we want to know where we stand....Read More
Anonymous Subcontractor
1 answerAdd commentApr 12, 2022
CaliforniaConstruction Contract
can I send one late? Can I still lien for non payment?...Read More
Anonymous Subcontractor
1 answerAdd commentApr 18, 2022
California
We started a job last November for mold removal and we still have not been paid on the work we did so now I want to excerise our lien rights onthis job...Read More
Anonymous General Contractor
2 answersAdd commentApr 18, 2022
California
Why is this notice not going thru? $624K fund to be provided to property owner for the material as a GC support fund/loan. ...Read More
Anonymous Subcontractor
1 answerAdd commentApr 15, 2022