California

I'm a subcontractor and need to get a waiver for paying a vendor. which one do i need?

1 reply

Mar 10, 2020
If its is a final payment, use a conditional waiver upon final payment if you have not yet paid them or an unconditional waiver upon final payment if you have already paid them. If it is a progress payment, use a conditional waiver upon progress payment if you have not yet paid them or an unconditional waiver upon progress payment if you have already paid them.