When do I file the next piece of the mechanic Lien?

ColoradoCollections

I am a general contractor did a project for an home owner here a few weeks back. He hasn’t paid. So through levelset I sent him a notice intent to file a lien it was mailed out on Oct 13 th 2021. When do I fill out the other actual mechanic lien paper and pay the $349?

2 replies

Oct 19, 2021
This makes no sense??
0 people found this helpful
Helpful
Oct 28, 2021
After the notice of intent is filed, you can record the lien on the 11th day.