UtahLien Deadlines

We are being withheld our retention on a project and our wondering if it's to late to put a mechanic's lien on the project?

1 reply

Oct 13, 2020

The deadline to file a Utah mechanics lien is generally 180 days after the completion of the project. If a Notice of Completion gets filed on the job, this deadline shortens to 90 days after when that Notice of Completion was filed.

For help calculating your deadline, this is a great resource: Levelset Mechanics Lien & Notice Deadline Calculator. For further discussion on Utah's mechanics lien rules and deadlines: Utah Mechanics Lien Guide and FAQs.