SC lien with a filing of 12/11/2020. Says there is a deadline for next action by 03/16/2021. What is the next action - ?? Thanks!
In South Carolina a lawsuit to foreclosure the mechanic's lien must be filed within 6 months from the last date of supply of labor or material to the Project or the lien is dissolved. So the next action you reference is probably the 6-month deadline.
Bond Rights and Lien Rights are not the same and filing one does nothing to help you with the other. I am happy to help. Please give me a call at my office to discuss as there are several details which we would need to go over to determine if we would be a good fit.