We've sent a 20 day notice with the original contract amount. Now we have change orders. Do we need to send new 20 day notices to reflect the new amounts?
2 replies
Nov 20, 2020
Generally speaking, no. The original notice will support the work done after that notice.
0 people found this helpful
Helpful
Nov 23, 2020
No, as long as your original notice was a correct estimate of the cost of the work at that time it is sufficient, unless you stop all work on the job for more than 60 days.