I’m a material supplier hired by the subcontractor and for the 2 month I missed a dead line What should I do? I’m negotiating my payments but they are taking a lo time what should I do?

1 reply

Dec 9, 2021

Hi Fernando,

If you are a subcontractor with a contract with the general contractor, one notice letter (commonly referred to as the third month notice letter) may be all that is necessary so long as it was sent timely. Any lawyer will need to analyze the situation to determine your lien options, but all hope is not necessarily lost.

Even where a lien is not available, you can still hire an attorney to issue a demand and/or file suit to recover what you are owed. It is very often the "squeaky wheel" that gets paid. 

Happy to discuss this with you further in a confidential call/setting.

Very best,

Ben House

281-762-1377

ben@houseperron.com

0 people found this helpful