the G.C. and Cowboy Grading both had a mutual agreement to terminate our contract at that point we turned in for our retainage to the G.C. the G.C. stated they could not pay us until the job was completed we were told it would be at the end of June. we continued to send a copy of the retainage request every month until the end of June at that time we were told that the new completion date would be Aug 24 when we contacted them on this date they said it would be another 180 days. the G.C. president called me a week later and said they were going to walk away from the job and a week later we got a letter from the G.C. stating the owners had sent them a notice of termination letter. what do we do from this point. thank you so much.

1 reply

Oct 2, 2019
If you have not already, you need to file a lien for retainage.  Have you already served the property owner and the GC with notice of withheld contractual retainage, which is the first step to perfecting a retainage lien.  Please call us at 817 442-5106 if you would like to discuss.  We are Board Certified Texas construction attorneys.  Robert Lovein, with Lovein Ribman.  www.loveinribman.com
0 people found this helpful
Helpful