Timeframe for filing lein/serving preliminary notice

California

Hello, I was the general contractor on a remodel in California a few months ago. I completed the project on December 16th. Is it too late for me to file a lein?

1 reply

Jan 27, 2020
You still have time. You have 90 days from completion assuming no notice of completion was filed or 60 days if a notice of completion was filed.
1 person found this helpful