Home>Levelset Community>Legal Help>The Angel Plumber did not perform the work as the city hall building safety's code. Thus, they scheduled to will come back on June 2nd 2020 to complete the work. Can they still put in a lien when they did not finish the job to collect the balance?
The Angel Plumber did not perform the work as the city hall building safety's code. Thus, they scheduled to will come back on June 2nd 2020 to complete the work. Can they still put in a lien when they did not finish the job to collect the balance?
The Angel Plumber did not perform the work as the city hall building safety's code. Thus, they scheduled to will come back on June 2nd 2020 to complete the work. Can they still put in a lien when they did not finish the job to collect the balance?