Menu
Home>Levelset Community>Legal Help>Revision to progress payment schedule

Revision to progress payment schedule

California

We need to revise our remaining payment schedule because of schedule changes to the remaining work. No change order to final project total. Do we need to update our contract to reflect these changes (much like we do on a change order)? Thanks!

2 replies

Jun 22, 2022

This would still technically be a considered a change order. Best practice would be to submit a wirtten change order outling the new payment schedule and the reason for the changes. 

2 likes
Jun 23, 2022
paper minecraft According to the contract, if you don't pay the fine, it's too horrible
0 likes

Add your answer or comment

Not the answer you were looking for? Ask your own question