My company filed the preliminary notice a year after starting the public works 33rd St Pipeline Project and now the Subcontractor isn’t paying invoices or returning communications. Will filing a stop notice be good? Preliminary notice delivered more than 30 days ago

1 reply

Sep 1, 2020

Good morning! Based on the above, it is likely that the preliminary notice would help you protect via the stop payment notice remedy the labor/materials furnished in the 20 day period prior to the date of servce of the preliminary notice. BUT you also may have a right to assert a claim against the public works payment bond despite a preliminary notice (subject to some surety defenses) as long as you send a timely "15/75 Day Notice."  