Preliminary lien amount

CaliforniaMechanics Lien

Can the general contractor ask me to omit the project amount on preliminary lien I send to property owner.

2 replies

May 23, 2021
He can ask you but you should decline. You need to fill in the estimated value of your work.
0 people found this helpful
Helpful
May 24, 2021
You must decline, in my view. Failure to include an amount does not put the owner on notice, which could render your lien, if necessary, voidable.
0 people found this helpful