on a mechanic's lien form in georgia, it asks for the date that the amount of lien became due. What is this date?

Georgia

Subcontractor. invoices not paid.

1 reply

May 18, 2021
The "date the sum became due" is actually construed to be the last date that you provided labor or materials to the project. Generally this would include any punch list work, but not any warranty work.