On a delay which is already commenced for the contractor, will employer delay still be considered concurrent?

AlabamaConstruction Contract

Hi, Thanks for the free help on construction contracts. Following is the scenario Contractor has delayed submission of drawings for approval. Original submission date (contractor's obligation) : 31st Jan 2020 Actual Submission: 30th March 2020 The approval for commencement of work from authorities (obligation of client): 5th Feb 2020 Actual permission was provided on : 5th April 2020 Can the contractor claim that the delay is concurrent? If so to what extent? Thanks Hariharan PS: this is Indian scenario. As there is no drop down option was available for outside US, I have chosen few dummy options