Menu
Home>Levelset Community>Legal Help>My client has ignored my notice of intent to lien. What's the next step?

My client has ignored my notice of intent to lien. What's the next step?

FloridaDesign ProfessionalMechanics LienPreliminary Notice

I'm a design consultant and project manager in Fort Lauderdale. We finished a project for a civic association board. As per our contract the balances due were to be paid upon completion. We completed a final punch list and a satisfactory final walkthrough. It has been over six months and we have not received payment despite our third billing invoice. I sent a notice of intent to lien via Levelset but that too was ignored though we received USPS notice of delivery more than 12 days ago. I would like to know what my next step would be to collect payment in the amount of $14.890.00 I understand that theft of services over $10K in the state of Florida is considered a crime. Should I proceed to file lien, or go directly to the police and file a report?

7 replies

Aug 25, 2021
What kind of work did your company do?
0 people found this helpful
Helpful
Aug 26, 2021

Under the facts described, this is not a crime and you will likely not have lien rights. I would need additional facts about your situation to advise you further. You have options, but without knowing more about the work you did, who the "civic association" is, whether this is a public or private project, etc., it is not possible to advise you properly.

1 person found this helpful
Helpful
Aug 26, 2021
713.08(5):  The claim of lien may be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the labor or services or materials by the lienor." And failure to pay a contract balance is not theft of services.
1 person found this helpful
Helpful
Aug 26, 2021
We did the design concept as well as the project management. Some of the funds owed are owed to our subcontractors for painting, tile installation and cleaning services. My company's role was to manage trades who were brought in by us as well as general management of the project including scheduling trades, deliveries, meetings and coordination of all trades involved.
0
Report Spam
Aug 26, 2021
The only reason I can think of for them not to pay is that they wanted us to obtain notarized lien release forms from every contractor and subcontractor involved who received payment on the job. We obtained most of them but some of the balances were paid directly to the trades by the association and we were not witnesses to them receiving payment. Those contractors did not provide final notarized lien release forms. Our contract with the association states that we will "request" these documents which we have several times, but that is all we can do as our due diligence. They had no problem with any of the work as we fulfilled a punch list and performed a final walk through which was satisfactory to the board. Our biggest problem here is that some of the balance owed is to go to our subs and they completed their work in good faith and satisfactory to the client.
0
Report Spam
Aug 26, 2021

The lack of sub lien releases may be why the association withheld payment, but that is not what will cost you your lien rights. As Andy noted, you have 90 days from final completion to record your lien. At six months, you are well past that deadline. But you may still have a claim against a bond or, failing that, against the association for breach of contract. You should consult an attorney (yes, pay for a consultation) to better understand your options.

1 person found this helpful
Helpful
Sep 3, 2021

My point is, a lien has to be filed within 90 days of the last performance of work on the project. Your question suggests the work has been complete and not paid for, for 6 months. If that is true, it would be too late to file a lien. However, if you’re recovering from an Association, the Association has assets and may well be collectible by simple civil lawsuit for breach of contract.

 

 

I’m very confused about your role on this job. I gather you’re some kind of design/build CM, and the association hired the trades directly. If so, then they’re not your subs and I don’t see why you would owe the owner evidence of payment of the trades.

 

 

If you hired the trades directly, the trades owe you lien releases when you pay them, and a GC shouldn’t hand a sub a check without getting a lien release handed to the GC simultaneously.

 

 

 

0 people found this helpful
Helpful