I'm a subcontractor that worked on a federal building project. Our last day on the project was 10/4/2019 but we still have not been fully paid. I used Levelset to send in a Miller Act Claim on 9/24/2020. What are the next steps we need to take to enforce our Miller Act Lien Rights?

1 reply

Oct 8, 2020

You should consult with a construction attorney, but you may have just missed your window to file suit on the bond (1 year from the date of last funishing) --- see https://www.levelset.com/blog/miller-act/ 

 You may still have a contract right against the prime contractor, of course. Again, I would consult an attorney as soon as possible!