WE FINISHED OUR WORK ON THE JOB 3 MONTHS AGO BUT HAVENT'S GOTTEN PAID. WHAT SHOULD WE DO? COSTS PLEASE

6 replies

Aug 3, 2021
Who hired you (owner, contractor, subcontractor)? Are you a company? What kind of work did you do?
0 people found this helpful
Helpful
Aug 3, 2021

HIRED ME A CONTRACTOR. A'M THE COMPANY- SUBCONTRACTOR

0
Report Spam
Aug 3, 2021

JOB TYPE: FURNISH AND INSTALL

0
Report Spam
Aug 3, 2021
Did you deliver a "notice to the owner" within 45 days of first furnishing materials to the job or starting work? If yes, you have 90 days from finishing the work to file your construction lien. If the answer to the first question is "no" then you do not have lien rights. If you are more than 90 days from finishing (not including punch-out) then you do not have lien rights. If you are without lien right you can file a lawsuit against the GC for not paying you. How much is owed?
1 person found this helpful
Helpful
Aug 3, 2021

NTO WAS SENT LAST YEAR 9/28/2020

THE DAYS DAY FROM THE JOB WAS 5/27/2021

0
Report Spam
Aug 3, 2021
OK. Looks like you have the right to lien. You can contact any construction lawyer in your area to get the lien done or you can contact my office by e-mail: basslawoffice@comcast.net. Don't wait. The deadline to file the lien is Aug. 25th. That date cannot be extended.
1 person found this helpful