I am a Subcontractor. I forgot to do a prelien on a project, The project has been completed but the contractor has only paid about 10% of it. Would like on some advice of what I can do in this situation.

1 reply

Aug 15, 2022
You can still bring a lawsuit on your subcontract against your contractor. If the money has been withheld for no good reason, you could be entitled to two percent interest per month, plus your attorney's fees.
1 person found this helpful