Home>Levelset Community>Legal Help>I want to make sure we put the amounts in correctly within our Lien we filed, Order number 3967540.

I want to make sure we put the amounts in correctly within our Lien we filed, Order number 3967540.

Nevada

We just placed a lien. The original amount of the contract was $312, 711.02. The amount of "added or changed work" is $77,084.28. The Total Contract Amount, at the end of the job is $389, 795.30. I've filled out the lien as follows: Total Contract Amount: $389,795.30 Amount of your Lien Claim: $137,963.29 Amount Paid To You To Date: $251,832.01 Total Amount of all added or changed work: $77,084.28 Should I have put the Total Contract Amount as the original contract ($312,711.02), instead of the Completed Total Contract of $389,795.30? The question is whether that affects the validity of the lien.

0 replies