I am a sub sub contractor and have progress payments oveerdue. What do I do?

Florida

more than 30 day overdue on multiple payment applications.

2 replies

Nov 29, 2020

First, if you're still within 45 days of when you first started work on the project, you should serve a notice to owner. You also should contact an attorney. You may have remedies under your sub-subcontractor agreement to help you get paid faster. 

0 people found this helpful
Helpful
Dec 2, 2020

Send a notice to owner. Wait 30 days. If still not paid, file a lien (but file within 90 days of your last work).

0 people found this helpful