In South Carolina, how long is a mechanics lien valid?

1 reply

Jun 17, 2020
Once filed, a South Carolina mechanics lien is only valid for six months after the last day the claimant furnished labor or materials to the project. This is a fairly tight window compared to other states; as the deadline to file is 90 days after last furnishing. Meaning, if the lien was filed at the latest date, claimants have only 3 months to resolve the payment dispute before filing a foreclosure action. If there is still time, one useful step to take is to send a Notice of Intent to Foreclose. This isn't a requirement under SC mechanics lien laws, but it provides the property owner one last opportunity to pay before you take them to court. Here are some other articles you may find helpful: