Menu
Home>Levelset Community>Legal Help>How long do we have to file a lien after sending prelien?

How long do we have to file a lien after sending prelien?

CaliforniaLien DeadlinesPreliminary Notice

We sent a final request for payment, then sent a preliminary notice/intent to file yesterday. How long do we have to file the actual lien if we need to move forward? Work began on 8-8-19 and ended 8-19-19, are we protected sufficiently?

2 replies

Sep 19, 2019
If you are a GC, you have until 11-18 to record the lien
0 people found this helpful
Helpful
Sep 20, 2019
First, you’re only going to be able to record a mechanics lien for work performed 20 days before you served your preliminary notice. Second, your deadline to record a mechanics lien is going to depend on whether you’re a direct contractor or subcontractor/material supplier and whether a notice of completion or cessation was recorded. Direct Contractors: No earlier than after the direct contractor has completed its work but no later than the earlier of: (1) 90 days after completion of the project; or (2) 60 days after the owner records a notice of completion or cessation. Subcontractors and Material Suppliers: No earlier than after the subcontractor or material supplier has ceased work but no later than the earlier of: (1) 90 days after completion of the project; or (2) 30 days after the owner records a notice of completion or cessation.
0 people found this helpful
Helpful