How does a home owner adjust incorrect information on a 20 day preliminary notice before acknowledging it?
3 replies
Sep 13, 2021
I'm not sure what you mean by acknowledging it. The preliminary 20-day notice is just something sent by a contractor to preserve lien rights and put the owner on notice of a possible lien if there is a problem with payment in the future. There is nothing for the owner to do when receiving the notice and no obligation to acknowledge it. Whether the error is material depends on what that error is
1 person found this helpful
Helpful
Sep 13, 2021
At the bottom of the form there is a section that states, detach (date and sign) here and send to claimant as acknowledgement of receipt. Do I need to send this?