How are your lien rights impacted if you deliver to a secure offsite warehouse specific for the project?

5 days ago

Mechanics Lien

Expert
Managing Partner Miller, Ross, & Goldman

Ultimately I assume your delivered materials and/or equipment were then transported to the project site for application/improvement, correct? If that’s the case, your rights aren’t negatively impacted. Be sure to file your Preliminary Notice within 30 days from the completion date, then your lien within 90 days from the last day of the completion month. The only way a supplier’s lien rights would be negatively impacted is if they’re unlicensed, in which case the right to lien is forfeited altogether.

Best of luck!

Your answer or comment: