Menu
Home>Levelset Community>Legal Help>Florida Lien Filing Rights - Last Day on the job

Florida Lien Filing Rights - Last Day on the job

Florida

I'm a subcontractor working on a FL project. Though the last day of materials and labor on the job was in March, we are still out there working on Controls to resolve issues. Does this extend the date of the lien filing rights?

1 reply

Jun 14, 2022
You have to serve your NTO within 45 days of first materials delivered/work performed or before final payment is made by owner.
0 people found this helpful
Helpful