We are a material supplier that delivered material on 6/15. We filed the initial notices, but missed the deadline to file a lien by 7 days. Can we still file? or did we miss our opportunity?
Good morning Jennifer,
Unfortuntely, the lien law is very specific as to when things have to be filed by. However, I would like to suggest reaching out to our Legal help with your situation, just to ensure that you are unable to file. They can be reached here