Menu
Home>Levelset Community>Legal Help>Do i still have any rights/

Do i still have any rights/

CaliforniaMechanics Lien

So i did not file a 20 day pre-lien. as client was making payments very fast and then we decided to seperate our ways and not continue working together. He still owes me money per the signed proposal and AIA contract. But now refuses to pay me. I did send the client a Mechanics lien

2 replies

Feb 26, 2021
If you were in direct contract with the owner, you do not need to serve a Preliminary Notice in order to record a mechanic's lien. You have 90 days after the recording of a mechanic's lien to file a lawsuit.
0 people found this helpful
Helpful
Feb 26, 2021

Thank you sir. Thats what i thought

0
Report Spam