We just recorded a Notice of Claim for Unpaid Contractual Retainage. Do I need to calendar any deadlines?

2 replies

May 31, 2023

Recorded a Notice of Claim for Unpaid Contractual Retainage where? You do not specify the nature of the project, whether it is commercial or residential or government -- all these factors make a difference.

You really need to retain a construction attorney to evaluate your situation and documents and to provide advice.

Good luck.

0 people found this helpful
Helpful
May 31, 2023

Typically 30 days and the lien Deadline is around 4 months after the project Completion date if you are Still having issues getting Paid from them My firm can Help facilitate on those liens to get you paid Feel free to reach out to me @ 972-872-8783 and I'd love to talk to you more about this 