KentuckyConstruction Contract

We are a domestic sub contractor for a main contractor handling the electrical installation in a building. CSC was issued to the main contractor but they refuse to issue to us. Can i know what are the implications? All my UPS, Gensets and transformer gears are expiring on warranties. Is there any recourse for me?

1 reply

Aug 30, 2022

It is going to depend on your subcontract language. In general, substantial completion depends on the Owner/GC contract, but you may have signed a subcontract with different requirements.

0 people found this helpful