My father was the sole owner of our company, now owned by myself and my 2 brothers. He signed a contract back in March of this year when we had plenty of employees to complete the work. The amount the project was bid for has drastically increased with the price inflation in the construction industry and the sub we had planned to sub the curb work out to has had to move on with commitments on other projects because this particular project keeps getting pushed by the owner from my understanding. I notified the GC already and they said we are responsible either we can find another sub or else we will incur the premium pricing it will cost for them to find someone else.