I sent out and invoice back in September of 2020. We also sent out a prelim notice.

1 reply

Mar 9, 2021
In Nevada, you can record a lien within 90-days of last providing labor and/or materials, or within the last day the Project was completed. If the Project was completed in September of 2020, your right to lien has lapsed. However, if the project just recently completed and you finished your work back in September of 2020, you still may have a right to record a lien.