Can I file a Mechanics Lien for an amount greater than the pre-lien?

CaliforniaMechanics LienPreliminary Notice

I am a building materials supplier. I sent a pre-lien for $110k on 7/18/22. The job is done, but I didn't realize how much was charged on their account. I have a balance of $243k that is past due. Am I able to file a mechanics lien for the entire amount? The last job was shipped on 11/8/22 for the amount of $108k.

4 replies

Jan 20, 2023

Yes, Scott, you ca record a lien in an amount that exceeds the estimated value in your preliminary notice. Your materials were all furnished to the same project that was identified in your preliminary notice, right?

0 people found this helpful
Helpful
Jan 20, 2023

I am the CEO of Wolfgang and Rhodes. I help contractors execute liens and get paid typically within 5 days. I charge nothing up front. Feel free to call my cell 214-518-9595 or email me at joshua@wolfgangandrhodes.com 

0 people found this helpful
Helpful
Jan 20, 2023

Are you able to have a phone call discussion with me to lead me down the right path on how to get paid?

0
Report Spam
Jan 20, 2023

I am available right now yes. 214-518-9595

0 people found this helpful
Helpful