Menu

Can I file a lien?

CaliforniaMechanics LienPreliminary NoticeRight to Lien

I'm a subcontractor, we finished the work on this project (this was change order) without the PO. Now our client is not paying. We filed preliminary notice 2 weeks late. What can we do now?

3 replies

Sep 17, 2020

It doesn't matter that the work was done without a PO. If you are owed money, and despite how long you waited to serve the 20 day prelim., record a lien before the expiration of 30 days after recordation of a Notice of Completion, or 90 days after completion if no NOC is recorded. Then, you have 90 days to file suit to foreclose on the lien. Call me if you would like to further discuss. Thanks, Andrew

1 person found this helpful
Helpful
Sep 17, 2020
Just to add to the above. A California preliminary noticecan be effective and valid if sent late. But it will limit that amount of lien rights to the value of labor and services provided in the 20 days preceding the notice, and everything provided thereafter. If you wish to proceed with your lien claim, you'll need to file within the deadlines cited by Andrew Carlton above. Good luck! For further resources, see:
1 person found this helpful
Helpful
Sep 17, 2020

The preliminary notice reaches back to cover labor and materials provided 20 days prior to the service of the preliminary notice and all labor and materials going forward. The next step would be to record a lien assuming it is still timely.


MARY A. SALAMONE
PARTNER

P. 949.381.6177 | F. 619.788.5522 | mary.salamone@procopio.com

1 person found this helpful
Helpful