I'm a subcontractor working on a commercial job. I finished my work in November 2021 and have not been paid.
1 reply
Jun 30, 2022
Whether you can record a lien depends on whether the project is complete and for how long, that is you must record a lien within 30 day of recordation of a notice of completion, or 90 days after completion, if no NOC was recorded. If time permits, and you served a 20-day prelim, you should record a lien asap.