Can I file a lein for a amount based on what my business would have made if I was not forced to stay on his site

MontanaBack ChargesBond ClaimsBonding Off Lien

I was framing a house for a contractor and Big Sky the concrete for the job was supposed to be done in May and was not completed until December and still not 100% completed the contractor refused to let me go do another job so that I can stay fed pretty much can I file a lien on the property in the state of Montana without filing a preliminary notice or can I still file the preliminary notice now he kicked me off the job on December 15 for not being there but he had the excavators tearing up the whole job site and multiple guys were injured from climbing over the mounds of dirt and alsoWe’re unable to work due to Covid that we believe they got from the architects secretary who was tested positive for Covid and came to our job site, several times I was asked to drive up to the job site which is an hour and a half drive to unload materials majority of the time they were not even for framing and I am the framing contractor also I had put in 178 man hours with my lift and my guys assisting the concrete guys and I was asked to do so by the contractor and they refused to pay me for it all the materials for the job have never been there And all the take offs for materials were not there or incomplete also his secretary coming to the job site knowingly positive for Covid and while doing so one of my workers had also gotten Covid recently after and his major complaint was that guys were not on site and the reasoning is because of Covid and because he had our job site torn apart by the excavators and multiple times have my guys been injured trying to work over and around the excavators this job was supposed to be a summer job early summer and it wasBid for that end it is now the middle of winter and concrete has just barely been finished and I have lost all my major contracts because of this and the months that I make all my money what are all my things that I can make the bond amount for on this lein

0 replies