Can client fire require me to pay for additional work after they have altered what I did.

Idaho

I need some advice on my rights as a contractor, and if I have the right to receive payment, if my customer has the right to fire me just cause they don't like my prices anymore, after they signed.

1 reply

Aug 9, 2021

Grounds for termination are typically defined within the construction agreement. However, if the agreement is silent as to the grounds for termination or if there wasn't a written agreement between the parties, one party typically cannot terminate an agreement with another party unless said party materially breached the agreement. A material breach is a breach that so substantial and fundamental that it defeats object of parties in entering into contract.  

0 people found this helpful