We're a subcontractor that completed a project and have not been paid by the GC. We have filed a mechanic's lien and it expires in January. Would like some advice as to what our next steps should be and whether it is worth us pursuing a lawsuit. Unpaid balance is about $36k

1 reply

Dec 9, 2021
Litigation is expensive, but you may get lucky. That is, sometimes just filing a lawsuit is enough to get paid. It's your call, of course. As for next steps, you need file suit within 90 days of having recorded your lien. Call me if you like. Good luck.