CaliforniaMechanics Lien

If a lien is filed e.g. August 1 2018 in the afternoon and an action is filed in court on October 31, does the fractional lien filing day count as a full day or is the following first full day when the counting begins? It's a matter of 90 or 91 days.....

1 reply

Jul 29, 2021
Morning or afternoon doesn't matter. The Code says: "The claimant shall commence an action to enforce a lien within 90 days after recordation of the claim of lien. If the claimant does not commence an action to enforce the lien within that time, the claim of lien expires and is unenforceable."