I need to release a Lien when a customer. All I need is the lien release document for Arapahoe county Colorado.
Please sent to Greg.cotton@hrti.com...Read More
I have a client that are not willing to pay us unless we reciprocally exchange check for unconditional release on final payment. We are located in California and I know that a Unconditional release will leave us without any rights if the check doesn't clear the bank. Are we allowed to add under Exceptions a note that states that this release is only valid upon funds positive deposit or something along these lines?
thank you.
Monica msafarik@icsinc.tv...Read More
Hello,
Is it possible to file a mechanics lien for unbilled change orders and retention? We have outstanding changes that haven't been approved yet so we are unable to bill for them. And typically we're not able to bill retention until the project has been completed. According to our project manager, all the changes are legitimate, the work has been completed. Our lien rights are going to expire soon so what would we need to do in this situation? Can we still file a lien for everything outstanding?...Read More
im currently coming near the end of a remodel on a lake resort style cottage like vacation spot, the owners have paid money towards labor and materials and had materials themselves to provide..time got stretched out waiting for there end of materials..cabinets,bathroom materials etc they are holding the last check untill completion understandably but there were substantial extras added on after the commencement of work and they are refusing to pay for our labor and any additional costs that caused....Read More
One year ago, my builder and I agreed that the final payment owed by us was $14,900. He was to finish the project by the end of May. Instead, it dragged on and was finally finished in March. He never made deadlines, and never sent any notice of changes in costs -- no change orders. He presented me with a bill for $34,000 last month, saying that costs had gone up in the ensuing year. I said I would only pay what we agreed, and sent him a check. He is now threatening a mechanics lien on our property by the end of this week if we don't pay up. ...Read More
Private funded project involving roadway improvements for a lot split. The city comes in and request additional work to the city water supply system. The additional work is under a separate contract with the city and is almost $50,000 . Additional work does not improve the property involved. It is performed by the same subcontractor but without any knowledge to the owner of the property in question. Can the Sub file a mechanics lien for the city requested extras without any preliminary notice being sent regarding the extra / separate contract work?...Read More
Im a subcontractor I gave a proposal to a general contractor, they liked our proposal, signed a contract and I sent out a preliminary notice. I've invested time and money into the project, we started working on the project in November 2021(shoring and bracing), the owners made major changes after they had already signed the contract and now they didn't accept the change order price and they decided to give the job to someone else. What happens when they have canceled the signed contract, are we to be compensated, we have not had a contract canceled before, we want to know where we stand....Read More
We started a job last November for mold removal and we still have not been paid on the work we did so now I want to excerise our lien rights onthis job...Read More