We are general contractors and own 1 parcel that is part of a 4-share well agreement. The well is on our property. Improvements needed to be done to the well and 2 of the 4 property owners refuse to pay. Can we send a 20-day intent to lien? ...Read More
Anonymous Contractor
1 answerAdd commentApr 29, 2022
Arizona
We have a septic installation business that is just one year old. We have a client that is refusing to pay $5,500.00 on a system that has passed State inspection and is fully functional. The payment was due on 5/3/2022 and was due upon receipt (Quickbooks Invoicing)....Read More
Anonymous General Contractor
Waiting for answerAdd commentMay 17, 2022
Texas
I am a loan broker who is trying to help a restoration company get back on its feet. It needs working capital because A/R payments are very slow. The owner loaded up on personal credit cards to provide working capital to his company. As a result, his credit score has tanked and banks are rejecting him. I believe we can get some relief if insurance companies will allow payments to the restoration company through a lockbox set up by the A/R factoring company....Read More
Anonymous Contractor
1 answerAdd commentApr 20, 2022
Maryland
When I send out CA Prelim's I have been listing my company (Pella Doors and Windows) as the "Material Supplier" BUT, we use 2 separate Pella approved General Contractor companies to do the actual installation. One of my co-workers is adamant that I should be listing us (Pella) as the Contractors (instead of being Material Suppliers). I just want to do it correctly in case we end up in a Mechanics Lien situation. Any clarification would be helpful. Lisolette Owens...Read More
Anonymous Material Supplier
2 answersAdd commentMay 16, 2022
California
I am material supplier for a job that we delivered 2/8 and 2/11. I didn't register it as I should have. We are now having collection problems. What are my next steps?...Read More
Helen Collins
Waiting for answerAdd commentMay 17, 2022
North Carolina
I am a general contractor working in Iowa, Illinois and Wisconsin. We do restoration work and in most cases invoice for emergency services when they are complete. Occasionally the lien deadline on emergency work approaches while the rebuild work is in progress. Does the lien deadline extend if we are still onsite performing work?...Read More
Amber Slamp
2 answersAdd commentMay 12, 2022
Illinois
we did a job but we didnt get paid. we filed a lien, lien was going to be expired on 05/10 but we filed a lawsuit on 05/06 is the lien still valid...Read More
Anonymous General Contractor
1 answerAdd commentMay 11, 2022
California
I'm not sure if this falls under supplier to supplier category, but I think it may. We are a materials supplier and are considering working with a concrete plant where the materials we supply and deliver will be blended into the concrete that is then delivered out to another job site. I believe we would fall as a Tier 1 supplier and my question would be can we file against the job where the concrete was delivered if we do not receive payment from the concrete plant who originally hired us to deliver the material to be blended?...Read More
Anonymous Contractor
1 answerAdd commentMay 11, 2022
TexasMechanics Lien
If I use a company to buy materials from for a project but I physically go to their location to pick up the material and they wanted to file a lien on me for not paying the invoice on time. Would that be based on the state their store is in and where I went to get the material or would that be based on the state my project is in. I did not provide a project address to them and they did not physically go there....Read More
Anonymous Contractor
1 answerAdd commentApr 13, 2022
MarylandMechanics Lien
Sub filed a mechanics lien on a Texas property that was labeled as homestead when filed (but not a homestead today). He also did not send any pre notices or notice that he actually filed a lien affidavit. What are my rights? The contractor was paid, but now learning they are related!...Read More
Anonymous Contractor
1 answerAdd commentMay 11, 2022
TexasMechanics Lien
I have a Architect that has a residential remodeling project in Maryland. ...Read More
Anonymous Contractor
1 answerAdd commentApr 19, 2022
Maryland
Im looking to foreclose a mechanics lien. I had levelset do the mechanics lien in Chicago , ILL. On the lien documents I noticed that the bank information was not placed on the lien. Will it effect my lien if i add the banking information.....Read More
Chris Rodriguez
1 answerAdd commentMay 11, 2022
IllinoisLien ForeclosureLien Priority
I am a subcontractor and the general contractor refuses to pay me even after a lien has been issued. If they bond it out to start receiving payment from the owner again, how do I make a claim on that bond. Also, how do I find out who has the bond? Thank you...Read More
Anonymous Subcontractor
1 answerAdd commentMay 3, 2022
South CarolinaBond Claims
We provided services for the customer last summer, the work order was not signed until November 2021 and they made their first payment in March 2022. We are unsure of which date to use when filing the mechanical lien....Read More
Sergio Rodriguez
Waiting for answerAdd commentMay 17, 2022
Texas