I received an email from my customer telling me that they are ready to pay me, but that I need to change my invoice to lower the price. I am sure I have the right amount and job completed according to the contract. I don't want to lose any more money with this people. What should I do? Can I file a lien now? ...Read More
Anonymous General Contractor
Waiting for answerAdd commentJul 25, 2022
UtahConstruction Contract
Here is my dilemma - I filed the lien and the company wrote me a check on 7/18/22, which I deposited. According to the bank, they have 7-10 business days to stop payment or cancel a check. They wanted me to sign an unconditional lien release, which of course I did not sign. The lien I filed will expire a few days before the check will clear, and I'm not sure how to proceed here....Read More
Claire Hardesty
Waiting for answerAdd commentJul 25, 2022
WashingtonMechanics Lien
We are small business in Hampton, VA looking for advice on proper terminology for applying late payment fees to unpaid or overdue client invoices....Read More
Christine King
Waiting for answerAdd commentJul 25, 2022
Virginia
We are a general contractor licensed in Illinois that been in business 40 years. We build items for museums and theme parks. In order to install our work at the Orlando area theme parks, we will need a FL GC license. With this new law, can we apply directly for a license, or do we need to take the test and register an employee in the state of FL to hold the license? We have opened an Office in Orlando and are a registered business in the state. I'm the VP of the Florida office and have 7 years experience of designing, fabricating, and installing complex structures in the theme parks for 2 state registered general contractors. Would that qualify as the 4 years of experience should I need to be the one to get the license?...Read More
Anonymous Contractor
1 answerAdd commentJul 25, 2022
Florida
We have a contract we are trying to dissolve due to the jobsite being delayed and general lack of communication. How can we quit?...Read More
Anonymous Contractor
1 answerAdd commentJul 16, 2021
WashingtonNotice of Termination
i'm an electrical sub contractor and i got lawsuit ith all the sub contractor was involve with GC to build the house. the house sold by the GC , was inspaction approve by the city and privet inspaction company by owner , and it all repair and approved by the owner inspactors . now he throuing lawsuit agens all subs after he build eligal structure as an additon . can he still swing as? ...Read More
Anonymous Property Owner
2 answersAdd commentJul 24, 2022
CaliforniaLawsuit
We are a GC in Ohio working on a project with a NOC that has not been completed and have been awarded a second project on the same property with a new contract. Do we file an amended NOC or a new NOC?...Read More
Anonymous Contractor
Waiting for answerAdd commentJul 25, 2022
OhioNotice of Commencement
I filed an NOC and the copy I got back had information that was changed. How do I revise the NOC so the information is correct? The owner address and company address are incorrect. ...Read More
Jenny Mclemore
Waiting for answerAdd commentJul 25, 2022
GeorgiaNotice of Commencement
I am in Ohio. If I start engineering work for a project, does that constitute my first day on the job with respect to the timing of the Notice of Furnishing? Also, same question with regard to ordering material. Will that count as my first day on the job?...Read More
Bob Babinec
1 answerAdd commentMay 7, 2021
OhioPreliminary Notice
We worked on a project for a customer and now we received 4 checks that are post marked. The first check was returned for NSF and just Friday we were able to deposit that check which was dated 7/7/2022. The check dated 7/21/2022 the bank is telling us that there aren't enough funds to deposit it. We also have two checks post dated to August 4, 2022 and August 18, 2022. The deadline to file a bond claim is 8/11/2022. Since we did get the funds for the first check should we file anything against our customer or what are our options to get this money sooner?...Read More
Terri Bumbalough
Waiting for answerAdd commentJul 25, 2022
TennesseeBond ClaimsMechanics Lien
Upon submitting a lien filing to Levelset there was an accidental submittal by the research team of an invoice that did not belong to our company. With that said, the lien filing is due on the following Monday and this has been realized on a Friday and this lien with the incorrect invoice has already been mailed to the county clerk. What are our options for amending this lien and still having it filed in GA ( where the property is located) with such a short time span between now and the deadline date? I should say that this would reduce the lien balance not increase it.. Thanks!...Read More
Matt Reece
2 answersAdd commentJul 22, 2022
GeorgiaCollectionsConstruction ContractLien DeadlinesMechanics Lien
Hi, we're structural steel fabricators and we have a project that has unpleasantly surprised us time and time again. We had issues with the galvanizing (was sent to a third party) and concrete step fabricators (third party) did such a poor job but due to the lack of time to get things redone we have had to fix and repair what we can as we go. Such repairs have been requested by the owner's rep because she doesn't want to wait another three weeks to get things redone. This has costs us extra labor but my boss is not concerned about that, he wants to complete the work and move on. He is more concerned with finding a way to protect ourselves from having to go back to fix more things or even redo the work once the job is approved and accepted. He's willing to do what it takes to get it right now but does not want to have to come back after the owner and designer have accepted the work and approved it complete. Is there a letter or any document that can help us with this?...Read More
Anonymous Subcontractor
1 answerAdd commentJul 14, 2022
CaliforniaConstruction Contract
I am currently in contract with a person who told me they were the owner of a building where we moved in to begin working today. According to the the prelien information, the property is owned by an LLC in Arizona. The person originally wanted me to make the contract in the name of the Arizona LLC, but I couldn't find the listing. Now that I have followed the links from the prelien from Levelset, I see the listing. Should our contract state the person or the LLC? Please let me know as soon as possible. I am also getting a feeling these people are not completely honest. Thank you....Read More
Amy Smith
1 answerAdd commentJul 18, 2022
CaliforniaConstruction Contract
I failed to file a preliminary notice and my sub did and they filed a stop notice. Does that mean I will have to pay them out even though I have not been paid?...Read More
Liz Kastlie
1 answerAdd commentJul 20, 2022
California
I am a General Contractor who focuses on Exterior Design and Remodel. I posted pictures of the progress and work done at the property (exterior only - no address visible) and our client is threatening us to take them off our social media/google page or he will file complaints and post bad reviews. This client is also refusing to pay the outstanding balance owed to us. We have a signed contract with this client and have performed all work as stated in agreement....Read More
Anonymous General Contractor
Waiting for answerAdd commentFeb 23, 2022
CaliforniaConstruction Contract