Bid Bonds in Construction

As a contractor grows and starts taking on larger projects, some jobs may require them to secure a bid bond. If you’re starting to bid on big jobs or public projects, you’ll become more familiar with bid bonds.

Until such a time, you’ll probably have some questions about what bid bonds are and how they work, and this guide can help.

What is a bid bond?

Bid Bonds

A bid bond is a guarantee, from a surety company to the project owner or GC, that the contractor will fulfill the contract obligations according to their bid. A bid bond is essentially the general contractor’s proof that they’re able to complete the project for the set amount. If the GC doesn’t complete the project as stated, the surety has to step in and make it right with the project owner.

There are three parties to a bid bond: the principal, the obligee, and the surety. The principal is the contractor purchasing the bond, while the obligee is the project owner or general contractor protected by the bond. The surety is the company providing the bid bond.

As a company grows and begins competing for bigger projects, particularly those in public works, a contractor will have to start posting bid bonds. These bonds act as insurance that you’ll do the work required for the amount stated in the bid.

Bid bonds and the Miller Act

The Miller Act requires contractors on federal projects to post certain bonds. While payment and performance bonds are the headlining stars of The Miller Act, bid bonds are also a requirement. On Miller Act projects, bid bond amounts are typically 20 percent of the bid’s value. 

How a bid bond works

When a general contractor needs a bid bond, they buy one from a surety for a certain percentage of the bid amount. Most of the time, this percentage is around 10 percent. (On federal projects, it’s set at 20 percent.) So, for a $500,000 bid, the contractor will have to secure a bid bond for $50,000.

That $50,000 serves as insurance that the contractor will complete the project for the $500,000 bid value. Should the general contractor win the bid but not take the project, the owner can place a claim against the $50,000 bond. 

The owner’s claim

Usually, the obligee’s claim will be in the amount of the difference between the original bid and the next bid the owner accepts. Let’s say the winning contractor bid $500,000, but fails to declines to take the job. If the bid from the next contractor was $525,000, the project owner can typically file a claim against the bond for $25,000. 

This fact in itself promotes competitive bidding. If a company submits a bid significantly lower than other bidders, the owner might think twice before awarding the project. With a value of 10 percent, the bid bond might not be enough to cover the difference between the awarded-but-failed contractor and the next competitive bid. This difference can have a significant effect on the project’s financing. 

Other reasons for bid bond claims

There are other scenarios in which an owner can place a claim against a bid bond. If the bid was inaccurate and the contractor needs to bill for more, the bond can serve as an overflow of sorts for the owner.

Also, if the contractor abandons the job while it’s in progress, the owner can use the bid bond to help pay the difference to have another contractor come in and take over.

Paying back a claim

The absconding contractor isn’t off the hook, though — this bond isn’t a standard insurance policy where a claim may or may not increase their monthly premium. Instead, the contractor has to pay the claim amount back to the surety, and the surety establishes the terms.

Getting a bid bond

While the consequences and insurances that a bid bond represents are serious business, securing a bid bond isn’t quite as difficult (or expensive). 

As long as a general contractor isn’t attempting to take on a project they can’t handle and they keep their finances in order, a bid bond shouldn’t be too difficult to obtain. However, the bond limit available to a contractor will depend on a number of factors, from their financial history to similar projects completed.

Bid bond requirements

Bid bond requirements differ a bit from job to job. While most federal-funded projects require bid bonds valued at 20 percent of the bid amount, other projects may require less. Private projects that opt for bid bonds — and public projects at the state and municipality level — often require bid bonds valued at 5 to 10 percent of the bid.

In general, their subcontractors aren’t expected to post bid bonds.

The application process

Contractors can apply for bid bonds through a surety agency. Most of the time, this agency will be an insurance company or bank. Establishing a relationship with an agency can help move bid bond applications along.

For smaller projects (let’s use $350,000 as the threshold), many sureties won’t require much more than a bid bond request form. This form will have the information necessary to apply for the bond. It will also allow the surety to check into the general contractor’s personal finances — the basis used to determine smaller bond eligibility.

However, for larger projects, the contractor might need to supply a bit more information with their application. In this case, the more useful information the contractor can provide, the better.

Breaking down the job costs, supporting bids from subcontractors, and quotes from materials suppliers can help. Also, the company’s financial reports, prepared by a CPA, can go a long way toward securing a bond.

Surety review

Once the surety receives the application, they’ll review it to determine whether the risk is worth the reward.

The first area the surety will look at is the contractor’s ability to complete the project, as that poses the greatest risk for their bond money. The surety will look at current projects, past projects, and the company’s history.

They’ll also take a look at financials. They’ll look at the contractor’s personal financial statements, corporate statements, lines of credit, and backlog of projects.  

The cost of a bid bond

The good news for contractors is that securing a bond large enough to cover a big project might not cost them much. In many cases, sureties issue bonds for flat rates between $100 and $500. 

For repeat customers with established relationships, some sureties will issue bid bonds for free. This courtesy is actually in hopes of securing the larger performance bond (often a requirement) if the contractor wins the project.

Bid bonds help ensure fairness

Essentially, bid bonds help keep everything fair. They ensure that general contractors aren’t submitting frivolous or unbalanced bids that they can’t live up to. Bid bonds protect the project owner from entering into a contract with a company that won’t take that project as-bid

They keep contractors from exaggerating their capacity or abilities, and stop contractors from changing their mind after entering their bids for a project.

In some ways, bid bonds also help keep bids competitive — an especially important point when it comes to projects paid for with taxpayer money.

Summary
Article Name
What Are Construction Bid Bonds?
Description
Construction bid bonds are required from general contractors on public projects and some private projects guaranteeing that the GC accepts the job as bid
Author
Publisher Name
levelset
Publisher Logo